Pilot-build records should let the team reconstruct what was built and tested. When a defect appears later, that history narrows the investigation and helps separate a design issue from a particular part lot, firmware image or assembly step.
REVIEW CHECKPOINTS
- Give each unit a stable identity
- Capture the configuration that matters
- Connect failures to disposition
- Review the record before the next order
Give each unit a stable identity
Assign a serial number or another unique unit identifier before final test. Use the same identifier on the unit, in the test result and in rework records. If the product has separate boards or modules, decide whether those subassemblies also need identifiers. The goal is to avoid test data that cannot be tied to a physical unit.
Capture the configuration that matters
At minimum, record PCB revision, assembly revision or BOM version, firmware build and test procedure version. Critical component lots may also matter when there is a sourcing change or a known quality risk. Avoid collecting fields simply because they are easy to collect; define which questions each field should help answer.
A firmware label such as “latest” is not sufficient. Record a reproducible version or hash that can be matched to the released binary. If a unit is reprogrammed after testing, update the record and repeat any affected tests.
- Unit and subassembly identifier
- Hardware and BOM revision
- Firmware image identifier
- Critical part or supplier lot, where relevant
- Test procedure version, result and timestamp
- Rework and retest history
Connect failures to disposition
For each failed or reworked unit, record the symptom, diagnosis, action, responsible person and retest result. If several units share a failure mode, use an issue record to connect them to one investigation. Do not overwrite the first failed result with a later pass: both are needed to understand the pilot.
Review the record before the next order
At the end of the pilot, confirm that the released configuration matches the tested configuration and that open exceptions have owners. Summarize the failure modes, rework effort and changes required before the next build. The Hardware Build Process page describes the release decision, while Hardware Build Records shows sample record formats.
General engineering guidance. Validation and acceptance criteria depend on your product and intended use.
